11 Jul 2016 | News

Landslide Dam Assessment in Chin State, Myanmar

2 mins Read

70% Complete

A team of scientists recently visited the landslide dam in Chin State, Myanmar to assess the risk associated with the dam and to develop a comprehensive management plan. Conditions of the lake, landslide dam features, dam materials, the river course and river bed materials were studied. The team observed the landslide dam is composed of loose and highly shattered shale with scattered sandstone boulders — materials easily eroded by rain water and highly permeable.

Experts Samjwal Bajracharya and Sudan Maharjan from the International Centre for Integrated Mountain Development (ICIMOD) and Vishnu Dangol from Tribhuvan University joined with the team from Chin State Forest Department. The group was invited by Dr Nyi Nyi Kyaw, ICIMOD Board member, Director General of Forest Department, Ministry of Environmental Conservation and Forestry and Dr Tint Swe, Director, Watershed Management Division, Forest Department Ministry of Natural Resources and Environmental Conservation.

Discussion with DG of Forest Department
Photo: Sudan Bikash Maharjan/ICIMOD

At present, the lowest freeboard, the height above the recorded high-water mark of the dam, is only 9 m and is expected to decrease rapidly during the monsoon season. Erosion and compaction will result in further reduction of the freeboard. The meteorological department forecasts at least one storm will occur in each month of this monsoon period and there is a strong probability of the dam breaching in this monsoon.

Most physical information was generated through remote sensing or collected in the field analysed through geographic information system (GIS). Combining and analysing remote sensing data and the field investigation, the ICIMOD team sees a strong possibility of dam breach during the monsoon. If the Chin Hill landslide dam breaks and causes a flash flood, additional land-slides may occur within 10 km downstream and debris deposits may continue further down-stream. Fortunately, no settlements or infrastructure exist along the river down until Yazagyo dam and reservoir, 52 km from the landslide dam. Damage should be minimal, however, the possibility of additional sedimentation is high.

The team recommended the installation of an automatic weather station (AWS) and an  automatic water level station (AWLS) with real-time satellite connection to monitor the precipitation and lake water level. Immediate installation of a flood warning system was recommended to keep people away from the river valley bottom down to the Yazagyo reservoir. Monitoring of lake water levels and dam conditions using web camera with an image feed is also needed to reduce risk. The team made a presentation to officials of Myanmar and briefed them on the their findings and recommendations.

Stay current

Stay up to date on what’s happening around the HKH with our most recent publications and find out how you can help by subscribing to our mailing list.

Sign Up

Related Content

Continue exploring this topic

A New Way Forward for Brick Kilns in Nepal

  The destruction of brick kilns caused by the massive earthquake earlier this April damaged approximately 110 chimneys in the valley. ...

27 Jun 2017 News
ICIMOD Hosts a Borlaug – Ruan Intern Sponsored by the World Food Prize, USA for the Fourth Time in a Row

AN ALL-EXPENSE-PAID, EIGHT-WEEK HANDS-ON EXPERIENCE, the prestigious Borlaug-Ruan International Internship provides exceptional high school students the opportunity to work with ...

14 Oct 2016 News
Better Business Practices in Surkhet

Twenty-five participants took part in ‘Entrepreneurship and Business Planning Training’ training in Surkhet 17-21 September 2016 as a capacity development ...

12 Oct 2015 HKPL
Pakistani students learn about permafrost and glacier monitoring

A two day workshop on permafrost and glaciers was held 15-16 September at Karakoram International University (KIU) in ...

30 Jul 2018 HI-RISK
Communicating flood early warning in the Ratu watershed

The team’s first stop was Bardibas, where ICIMOD has set up a community-based flood early warning system (CBFEWS) on the ...

CCAC to support brick study in Nepal

The 7.8 magnitude earthquake that hit Central Nepal on 25 April 2015 and the more than 300 aftershocks that followed, ...

29 Mar 2016 Gender in Koshi
Mainstreaming Gender and Livelihoods into Water Management

Linking livelihoods and gender issues in the Koshi river basin can improve water resource management, was the key message of ...